Send Construction Change Directive dialog box
Use this dialog box to send an existing construction change directive to other contacts to review, and create a new outgoing transmittal for the construction change directive. You can also forward the files included with the construction change directive electronically via email or Info Exchange.
To
Click to open the Choose Project Team Members dialog box to select who to forward the construction change directive to. You can also type email addresses directly in this field.
CC
Click to open the Select Project Team Members dialog box to select who else to forward the construction change directive to. You can also type email addresses directly in this field.
Contacts in the CC field will receive a link to download the files, but will not be sent reminders.
From
Click to open the Choose a Project Team Member dialog box to select the project team member who is forwarding the construction change directive. You can also type email addresses directly in this field.
Subject
The subject of the original construction change directive. You can edit it.
Purpose
Select the purpose of the construction change directive from the drop-down list.
Hide Recipient List
For Info Exchange transfers only: Mark this checkbox if you want to hide the list of recipients on email notifications, forms, and transmittals, If this option is not checked, then the email notifications, forms, and transmittals will contain the To: and CC: contacts.
Date
The date the construction change directive is being forwarded. You can edit it.
Send Via
Select the construction change directive's transfer method from the drop-down list.
If you choose an electronic transfer method (Info Exchange or a drag and drop method) you will be required to add files before you can file the transmittal.
Log in Document Control
When a file has been added to the this item through the Associated Files/Files to Send tabs using Include Files From > Record Documents, marking this checkbox will log the file's record document as Issued in the Document Control activity center (the revision's Revision State changes from Draft to Issued) and the Last Issued date is logged.
Transmittal ID
The ID for the transmittal linked to this construction change directive.
Construction Change Directive ID
The construction change directive's ID number.
Remarks tab/Construction Change Directive Summary tab/Description of Contents tab/Files to Send tab/Email Log tab/Related Items tab/Change Log tab
Refer to the Forward Construction Change Directive for Review dialog box for a description of these tabs.
Keywords
Click to open the Choose Keywords dialog box to apply keywords to the construction change directive.
Click to spell check the fields in this window. If any mistakes are found, the Spelling Check dialog box opens with spelling suggestions.
Print or Email Form After Filing
Mark this checkbox to open the Transmittal form, which you can review and print immediately after filing the construction change directive, and a transmittal email message in Microsoft Outlook (if you sent it via email) to send to the contacts in the To field to notify them that the construction change directive has been forwarded.
Options Tab
Use this tab to edit the settings for the transmittal sent via Info Exchange or via Email. The available options depend on which method is selected.
Create and Transfer/Create and Send
Click to send the construction change directive. The events that occur depend on which option you chose in the Send Via field.
If you chose to send it via Info Exchange:
● The original construction change directive remains in its current category.
● The Sent action is added to the construction change directive's Change Log tab.
● The file transfer is logged in the All Outgoing log of the Info Exchange activity center.
● The transmittal is filed in the All Sent log of the Project Transmittals activity center.
If you chose to send it via Email:
● An email message opens in Microsoft Outlook containing the files and information about the file transfer. Edit the message, then send it.
● The original construction change directive remains in its current category.
● The Sent action is added to the construction change directive's Change Log tab.
● The transmittal is filed in the All Sent log of the Project Transmittals activity center.
Create Transmittal
This button appears if you selected a physical transfer method (such as Fax) in the Send Via field. The following events occur:
● The original construction change directive remains in its current category.
● The Sent action is added to the construction change directive's Change Log tab.
● A transmittal is filed in the All Sent log of the Project Transmittals activity center.
To access this dialog box
Select a construction change directive, then click Send from the Tasks panel of the Construction Change Directives activity center.
Table of Contents
Index
Search (English only)
Back