Change Orders Log
This page shows all change orders for the current project. Click the subject of a change order to view its details.
This page is available only if you are an internal (Project Center) user.
To only see change order actions assigned to you, select the My Change Order Actions log. To only see change orders which you are expecting or are expected from you, select the My Expected Change Orders log.
Change Orders categories
Use the Change Orders drop-down list to filter the list of change orders by category. The categories are as follows:
All
This category lists all change orders that have been logged for this project.
Pending Incoming
This category lists change orders that were sent via Info Exchange and need to be downloaded in Project Center.
Under Review
This category lists change orders that have been received, but responses have not been sent to the change order senders.
When a non-expected change order is first filed, it is placed in the Under Review category.
Awaiting Action
This category lists change orders that have been received, but they:
● Have not been forwarded for review, or
● Have been forwarded for review, but a response has not been received, or
● Have been forwarded for review and all responses have been received, but there has been no response sent to the change order sender.
Forwarded for Review
This category lists change orders that have forwarded for review with due dates for other contacts to review that have not been received back yet.
Response Overdue
This category lists change orders that have been sent out for review but the responses from the reviewers are overdue.
Expected
This category lists all change orders logged as Expected.
Expected Resubmission
This category lists expected change orders that were created for change orders that require the sender to resubmit the change order (the action taken on the change order was Rejected or Revise and Resubmit).
Late
This category lists expected change orders that are overdue.
All Closed
This category lists change orders that have had a response sent to the change order sender and no further action is required.
Columns
Overdue
The icon displays to the left of change orders that are overdue.
ID
The ID number of the change order.
Sender ID
The number the contractor gave to the change order.
Subject
The subject of the change order. Click to open the Change Order page.
Total Days
The number of days to process the change order. The count starts from the start date, which is either when the item was created or the received date, and ends either now or when it was closed if a closed date was entered. If it is re-opened, it displays the count from when the change order was created. It is based on calendar days (not business days) and does not consider holidays in its calculations.
Received
The date the recipient received the change order. The field also displays the change order purpose and who sent the change order.
Forwarded
The date the change order was forwarded. The field also displays the purpose for which the change order was forwarded.
Response
The date of the change order response. The field also displays the action taken for the change order and the name of the user who sent the response.
Closed
The date the change order was closed. The field also displays the action taken for the change order and the name of the user who closed the change order.
Supporting Documents
Displays the number of supporting documents associated with the change order. There are two possible icons that may appear in the field:
Click to download files attached to many project items directly from the log page.
Click the image to send a request to the owner to repost the files. when the files have been removed from Info Exchange. This occurs when the transfer item has expired.
Related Items
Displays icons for any project items related to the change order. Click in the column to access the Related Items popup window, shown below. Click the hyperlink for a related item to view its details.
Tasks
The Tasks drop-down list displays available tasks that can be performed for the change order. Select a task from the list as needed.
Log Page Tools
The following tools are available in the Change Orders Log toolbar. For more information, refer to Log Page Tools.
Export
Click to export the items in this log.
Show/Hide Column Filters
Click to toggle on/off the column filters.
Show/Hide Group By Panel
Click to toggle on/off the group by panel.
Show/Hide Columns
Click to access the Field Chooser to add or remove columns from the log grid.
To access this page
From the toolbar, click View > Contract Management > Change Orders.
If change orders are not available to you, see Make a Project Center Project and Its Activity Centers Available on Info Exchange.