Change Order Proposals Activity Center
AKA Change Estimates or Potential Change Orders.
Use this activity center to create, log, review, and track change order proposals electronically.
Project Center administrators can set which tasks appear here using the Remove Contract Management Item Tasks dialog box. Change Order Proposals● New Change Order Proposal > Create Change Order Proposal Click to open the Create a Change Order Proposal dialog box to create a new change order proposal or to file an expected one. ● New Change Order Proposal > Log Received Change Order Proposal Click to open the Log a Received Change Order Proposal dialog box to log a change order proposal that you have received. ● Create Report Click to open the Create Report dialog box to select the type of change order proposal report to create. The report contains the contents of this log. You can customize which columns appear in reports simply by selecting which columns to show and hide in the activity center. Simply right-click on column headers to add or remove columns. A checkmark indicates the column will appear in the activity center and the report. ● Import Spreadsheet Click to open the Select Spreadsheet dialog box to select a Microsoft Excel spreadsheet containing change order proposal data that you can import. The imported change order proposals are placed in the appropriate change order proposal log based on the type imported. ● View Pending Items This task appears only when there are Pending Review Response change order proposals. Click to list only Pending Review Response change order proposals. Selected Change Order ProposalThe following list shows all available tasks for all change order proposal categories, in alphabetical order. The tasks that appear depend on which category you select from. ● Add Similar Change Order Proposal Click to create a new change order proposal
based on the one selected. The new one contains most of the information
from the original, except for unique identifiers such as the ID.
The new one is also automatically related
to the original. Supporting documents
from the original are included. If the original contains a receive action with files and/or description of contents entries, the Select Files and Description of Contents dialog box opens first, enabling you to select the items to include in the new copy. ● Close > Close Click to open the Close Change Order Proposal dialog box to close the change order proposal without providing a response. ● Close > Respond and Close Click to open the Respond to Change Order Proposal and Close dialog box to file your response to the sender of the change order proposal and close it. If the change order proposal has files associated with it, the Select Files to Send dialog box will open first. ● Close > Send and Close Click to open the Send and Close Change Order Proposal dialog box to send the change order proposal to team members and close it. If the change order proposal has files associated with it, the Select Files to Send dialog box will open first. ● Delete Click to delete the selected change order proposal from Project Center. You must be a Project Center administrator and have a contract management role to delete change order proposals. ● Forward for Review Click to open the Forward Change Order Proposal for Review dialog box to forward the change order proposal to any contacts who are responsible for reviewing the change order proposal and to create a transmittal. If the change order proposal has received files or supporting documents associated with it, the Select Files to Forward for Review dialog box will open first so you can select the files to forward. ● Modify Click to open the Modify Change Order Proposal dialog box to edit the settings for the selected change order proposal, including due dates, email message reminder settings, and the description. ● Receive Click to open the Receive Change Order Proposal dialog box to log the receipt of a change order proposal that you were expecting. ● Receive Pending Change Order Proposal Click to open the Log a Change Order Proposal dialog box to receive a change order proposal from Info Exchange. ● Receive Pending Review Response Click to open the Record Reviewer Response for Change Order Proposal dialog box to record a response received about a change order proposal via Info Exchange. ● Record Reviewer Response Click to open the Record Reviewer Response for Change Order Proposal dialog box to record a response received about a change order proposal that you forwarded to other contacts. When you receive a response back from a contact, record it using this task to track its progress. ● Reopen Click to open the Re-Open Change Order Proposal dialog box to re-open the closed change order proposal. ● Review Related Action Items This task is available only when you select an item that has related action items. Click to open the Related Action Items activity center to view action items related to the selected item. ● Review Related Markup Sessions This task is available only when you select an item that has related markup sessions. Click to open the Related Markup Sessions activity center to view information about and preview the related markup sessions. ● Send Click to open the Send Change Order Proposal dialog box to send the change order proposal to other project team members. ● Send Email About Change Order Proposal > To Sender Click to open an email message in Microsoft Outlook to send to the contact who originally sent the change order proposal. The email message includes information about the change order proposal. ● Send Email About Change Order Proposal > To Recipients Click to open an email message in Microsoft Outlook to send to the original change order proposal recipients as a reminder or with additional information. The email message includes information about the change order proposal. ● Send Email About Change Order Proposal > To All Reviewers Click to open an email message in Microsoft Outlook to send to the contacts who are currently reviewing the change order proposal, as a reminder or with additional information. The email message includes information about the change order proposal. ● Send Email About Change Order Proposal > To All Participants Click to open an email message in Microsoft Outlook to send to all change order proposal participants, including the sender, recipients, and reviewers as a reminder or with additional information. The email message includes information about the change order proposal. ● View Form Click to open the Change Order Proposal form to view or print the selected change order proposal's history and details. Selected ActionAccess the actions by clicking the expand The file tasks apply to files in the Supporting Documents tab. See File Tasks panel for more information. See Email Tasks panel for more information. See Related Item Tasks panel for more information. |
Change Order ProposalsCategory drop-down listThe category drop-down list contains filters to display the change order proposals in particular categories. For example, if you want to view overdue change order proposals, select Overdue from the list. Only overdue change order proposals will appear in the log. You can also choose to display change order proposals for all project users or only change order proposals on which you are listed as the sender or recipient. Each category is explained below.
AllClick to display all change order proposals that have been entered for this project. Pending IncomingClick to display all change order proposals sent via Info Exchange that need to be received. When a change order proposal or change order proposal response is logged by a project team member on Info Exchange, it will show up in this category. DraftClick to display all change order proposals that are in draft form and have not been sent. Under ReviewClick to display change order proposals that have been received, but responses have not been sent to the change order proposal senders. When a non-expected change order proposal is first filed, it is placed in the Under Review category. Awaiting ActionClick to display change order proposals that have been received, but they:
Forwarded for ReviewClick to display change order proposals that have been forwarded with a due date for another contact to review that have not been received back yet. Response OverdueClick to display change order proposals that have been forwarded but the responses back from the reviewers are overdue. OverdueClick to display change order proposals that were received with a due date but have not been closed yet. ExpectedClick to display all change order proposals filed as expected. Expected ResubmissionClick to display expected change order proposals that were created for change order proposals that require the sender to resubmit the change order proposal (the action taken on the change order proposal was Rejected or Revise and Resubmit). LateClick to display expected change order proposals that are late. All ClosedClick to display change order proposals that have had a response sent to the change order proposal sender and there is no further action required. Filter All ColumnsYou can filter by any text that appears in any of the columns in the log. For example, if you know the subject (or part of the subject) of the change order proposal that you are searching for (or the ID, status, due date, etc.), enter at least part of the text in this field. The change order proposals list updates automatically as you type. For example, if the change order proposal you are searching for has the number 30 somewhere in one of the columns, enter 30 in this field. The list will be narrowed down to only change order proposals that have the number 30 somewhere in one of the columns. Click to clear all filters.
Click to toggle between showing and hiding the column filter fields.
|
Add |
Click to open the Add Email Messages dialog box select an email message to add to the current change order proposal. |
Remove |
Click to remove the selected email message from the change order proposal. |
Supporting Documents tab
Use this tab to attach files to the selected change order proposal, and to view attached files. For example, if you receive a change order proposal and a particular drawing is related to it, you can use this tab to attach the drawing file to the change order proposal. Another example is if you receive a file with a change order proposal, mark it up, and want to send the marked up file to a reviewer. Also, files sent using the Add to > Change Order Proposal task are added to this tab.
The number in parentheses indicates the number of files that are attached to the change order proposal.
You can copy and paste and drag and drop files from Windows Explorer into this tab.
Change Version |
If you are using an EDMS, click to select a specific version of the file to link to the change order proposal. |
Set Order |
Click to open the Set Document Order dialog box to set the order of the documents. |
Add Files > Another Project File |
Click open the Add Supporting Documents dialog box to locate and attach a file to the change order proposal. |
Share with External > Yes |
Click to allow the selected files to be shared with external project team members through Info Exchange. |
Remove |
Click to remove the selected supporting file from the change order proposal. |
Preview tab
A preview of the selected file appears here.
Related Items tab
This tab lists all related Project Center items for the selected file.
Related Items tab
This tab lists all related Project Center items for the selected change order proposal.
Create Related > Action Item
Click to open the Identify an Action Item dialog box to create a new action item and link it to the current change order proposal.
Create Related > Transfer > Via Email
Click to open the Send Files to Email Recipients dialog box to send project files via email. Nothing is logged in this tab.
Create Related > Transfer > Via Info Exchange
Click to open the Transfer Files to a Newforma Info Exchange Server dialog box to transfer project files via your Newforma Info Exchange Server and link the transfer to the current change order proposal.
Create Related > Transmittal > Via Email
Click to open the Send Files and Create an Outgoing Transmittal dialog box to send project files via email, file an outgoing transmittal for a file transfer, and link the transfer to the current change order proposal.
Create Related > Transmittal > Via Info Exchange
Click to open the Transfer Files and Create an Outgoing Transmittal dialog box to transfer project files via your Newforma Info Exchange Server, create a new outgoing transmittal for the file transfer, and link the transfer to the current change order proposal.
Create Related > Contract Management > Contract Management Item
Click to open the Create Contract Management Item dialog box for the type of contract management item you selected to create a new CM item and link it to the current change order proposal.
Create Related > Web Link
Click to open the Create Web Link dialog box to enter a web link and automatically relate it to the selected Project Center item. After it is created, the Relation Type column will indicate Web Link, and users can double-click on it to open the website.
Relate to >
Click to select an existing project item and establish a relationship between it and the currently selected change order proposal. This gives you the ability to link two items that are related together (for example, a markup session that is related to a change order proposal). Select Another Project Item to open the Select Project Item dialog box to locate an item that is not in the list. When you create a relationship between two items, each item's icon is added to the other item's Related Items column and tab.
Share with External
Click and select Yes to allow the selected web link to be shared with external project team members through Info Exchange.
Remove
Click to unlink and remove the selected project item from the Related Items tab.
Removing a related item from the Related Items tab does not remove it from the database.
The Relation Type column has two icons to indicate the relationship type:
● The
icon indicates that the relationship
was created by a user and can be deleted (such as an action item
related to a change order proposal).
● The
icon indicates that the relationship
was created by Project Center and cannot be deleted (such as a
transmittal or record copy related to a change order proposal).
Change Log tab
This tab displays a history of the actions taken on the change order proposal, including when it was created, modified, who was involved, and any details.
To access this activity center
Click Change Order Proposals from the Activities list or from the Project Home activity center.
Table of Contents
Index
Search (English only)